范文一:通风空调工程质量控制
通风空调工程质量控制
摘要:随着现代信息化发展和不断的科技创新,人们对于生产生活
的环境要求越来越高,对环境工程的要求也越来越严格和重视,所以对于
通风空调工程施工的技术和质量提出了更为苛刻的要求。同时,质量问题
也往往与安全事故有直接联系,所以,工程中质量管理显得极为重要。随
着社会的发展及法律法规的不断健全,工程质量控制的手段及监督措施也
在不断完善,但是由于经济成本、人员素质、设计的多样化等原因,通风
空调工程质量控制还有些不尽人意的方面。笔者通过自身在实际工程中的
实践经验对通风空调工程的质量控制进行了系统总结,希望对于从事通风
空调质量管控的人员及施工企业提供些许借鉴作用。
关键词:通风空调;工程质量;控制
Abstract: with the development of modern information and continuous innovation of science and technology, people for production and living environment demand is higher and higher, to the requirements of environmental engineering is becoming more and more strict and attention, so for the ventilation and air conditioning engineering construction technology and quality put forward more stringent requirements. At the same time, the quality problems often also and safety accidents have direct connection, so, engineering quality management is very important. With the
development of society and the laws and regulations, perfect, engineering quality control methods and measures of supervision is being perfected, but because of the economic cost, personnel quality, design and other reasons, the diversification of ventilation and air conditioning engineering quality control still have some unsatisfactory aspects. The author through the practice of their own in the practical engineering experience of ventilation and air conditioning engineering quality control systematically summarizes, hope for ventilation and air conditioning in the quality control personnel and construction enterprise to provide some reference.
Keywords: ventilation and air conditioning; Engineering quality. Control
中图分类号:TK284.8文献标识码:A 文章编号:2095-2104(2013)
引言
通风空调工程是现代建筑工程的必要组成部分。随着现代信息化发展
和不断的科技创新,人们对于生产生活的环境要求越来越高,对环境工程
的要求也越来越严格和重视,所以对于通风空调工程施工的技术和质量提
出了更为苛刻的要求。同时,质量问题也往往与安全事故有直接联系,所
以,工程中质量管理显得极为重要。随着社会的发展及法律法规的不断健
全,工程质量控制的手段及监督措施也在不断完善,但是由于经济成本、
人员素质、设计的多样化等原因,通风空调工程质量控制还有些不尽人意
的方面。笔者通过自身在实际工程中的实践经验对通风空调工程的质量控制进行了系统总结,希望对于从事通风空调质量管控的人员及施工企业提供些许借鉴作用。
通风空调工程质量的事前控制
通风空调工程施工质量的事前控制与所有工程的事前准备工作相同,主要包含以下几个方面:a.图纸会审及与设计院的沟通;b.技术交底及安全交底;c.进场材料的质量把关;e.机械设备的选择及保养。
1.1图纸会审及与设计院的沟通
施工企业在进行通风空调工程施工准备工作中,首先是安排技术人员对所实施工程的图纸进行会审,从技术层面了解所承接工程的工程范围、施工内容、技术要求、材料要求等。在技术人员了解工程概况的情况下,才能提出工程所需的材料计划、机械设备需求、施工工法的选择、特种人员需求及劳务的总需求量等,以达到设计要求的质量标准及相关要求。另外,图纸会审还应该了解设计对于该工程的设计原理,对于每个系统所选用的各相关设备的要求、控制方式、动作原理等,同设计确认清楚,以便设备选型能够做到完全符合标准,避免由于设备选型有误带来后续调试时出现问题。后期调试过程中的不符合要求对于施工企业的更改难度非常大,所以施工企业要尽量避免,把施工图的图纸会审做扎实。如对图纸中每个通风空调系统的风机设备、空调设备的参数详细了解,统计风阀、风口设备的技术要求、控制方式、是否要求有调节风量功能、安装方式等等,以利于选型。同时,图纸会审要确认防火分区、防烟分区的划分原则及与防火分区和防烟分区相关的技术和质量要求。预留孔洞、预埋件作为通风
空调工程中必有的部分,图纸会审时应现场踏勘比对,有问题及时提交监理及设计单位进行解决。
1.2技术交底及安全交底
在工程进行施工前,技术负责人要对所有参与施工的人员进行技术交底及安全交底,并要求带班工长要有一定的技术水平,了解通风空调工程施工的基本原理和原则,严谨施工人员盲目作业。技术交底内容要求表明质量标准要求、施工参考图集做法及质量控制要点,如对于风管的加工制作要求、法兰的匹配互换性要求、风阀与风管的连接要求等。安全交底中除明确施工作业中应注意的安全问题及采取的安全防护措施外,还应该将质量与安全的联系加以说明。对于工程的功能性和使用安全性,往往由于质量的问题而导致安全事故的发生,例如消防质量安全事故、高空作业质量安全事故等等。
1.3进场材料的质量把关
进场材料的质量同整个工程的质量息息相关。对于工程所使用的原材料、成品半成品、构配件等要进行严格的检查验收,建立管理台账,进行收、检、发、储、运等各环节的管理制度,避免混乱和不合格的原材料使用的工程上。例如针对风阀防火阀的不同种类、不同型号、不同系统进行存放,避免由于管理混乱而造成混用,影响工程质量。当然如果分类太细,会影响仓库使用效率,增加库管员的工作量,所以应根据场地实际情况酌情分类存储。但是对于每单位原材料、设备必须进行有效的标识,严格按照标识进行收发领用。
1.4机械设备的选择与保养
机械设备包括施工机械设备、工具等。要根据不同的工艺特点和技术要求,选用合适的机械设备和工具;正确使用、管理和保养好机械设备、工具。为此要健全“人机固定”制度、“操作证”制度、岗位责任制度、交接班制度、机械设备检查制度等,确保机械设备处于最佳使用状态,保证设备精度、使用安全,保证施工质量满足精度要求。如风管制作加工设备的精度控制、维修与保养;红外线定位仪的精度控制等。
通风空调工程的事中质量控制
事中质量控制是指在施工过程中进行的质量控制。事中质量控制的策略是全面控制施工过程,重点控制工序质量。
2.1施工企业应认真做好工序的自检、互检、交接检检查。企业自检是发现质量问题的主要来源,但是要杜绝只查不改,或改不到位。如风管加工制作过程中,加工人员要自检风管成形标准、法兰平面度、风管密封性、风管咬口牢固性、螺钉间距等等。风管加工好进行安装前应有技术人员进行交接检查,确认前一工序质量合格再进行下一工序。
2.2工程施工过程中要设置质量控制要点。质量控制点是为了保证作业过程质量而确定的重点控制对象、关键部位或薄弱环节。质量控制点的设置是保证施工过程质量的有力措施。通风空调工程的质量控制要点如下。
1)风管制作
a.风管外形质量,应表面平整、咬口牢固、无严重划痕、法兰平面度符合要求、螺钉螺孔间距满足标准、尺寸偏差在安装精度范围内。风管密封应严密,以板材连接密封为主,辅以密封胶嵌缝,密封胶应符合环境要
求,宜涂覆在风管的正压侧。
b.矩形风管弯管的制作,一般应采用曲率半径为一个平面边长的内外同心弧形弯管。当采用其他形式的弯管,平面边长大于500mm时,必须设置导流片。
c.风管加固符合标准规范要求。
d.大边长碳钢焊接风管宜采用氩弧焊,并矫正焊接变形,加固可靠。
2)风管及部件安装
a.风管连接间的密封条应符合消防及空调通风系统的规定。密封条厚度根据风管的连接方式确定。对于承插连接的复合风管由于连接间距较小,可以采用密封胶作为密封连接介质。
b.风管与风阀部件的连接应采用螺栓连接,螺栓规格应根据风管边长不同按照相关图集进行选择,尤其是防火阀,禁止使用自攻螺丝连接。在定做防火阀时,应将风管与风阀法兰的螺孔制作规则统一一致,保证互换性,避免由于不匹配而造成的质量问题和影响工作效率。
c.风阀安装应设置独立支吊架,尤其是边长大于630mm的防火阀,避免因火灾时风管变形而影响性能。支吊架形式参照图集制作。防火阀的安装方向、位置应正确。防火分区隔墙两侧的防火阀,距墙表面不应大于200mm。防火阀的易熔片应朝向火灾危险性较大的一侧。
d.远控多页排烟口(送风口)的安装注意事项。由于排烟口(送风口)由带有一定厚度的阀体和铝合金风口组成,所以排烟口(送风口)安装于风管上时,应从风管开口处安装法兰与排烟口(送风口)连接,禁止直接将排烟口(送风口)安装与风管内部,影响风管通风面积,或将风管开口
处制作与排烟口(送风口)厚度相同的风管短管,将排烟口(送风口)安装于短管内,并使用螺栓或自攻螺丝连接牢固,密封严密。为防止排烟口(送风口)的重量过重导致风管变形或受损,排烟口(送风口)宜单独设置吊架。其远控装置安装应引下至适当位置,控制缆绳使用金属套管,弯曲半径不小于250mm,弯曲不应多于两处,并应配合装修要求做到美观实用。
e.风管穿越墙体时,预留孔洞的尺寸应比风管截面的每边尺寸大100mm,并用不燃且对人体无危害的柔性材料封堵。由于风管安装单位与墙体砌筑单位往往不是同一施工企业,平行施工时要求单位之间配合密切,并应做好成品保护工作。
f.风口安装时应符合规定要求。对于镂空吊顶内安装的风口,需要注意风口的安装位置不得与装修吊顶的部件重叠,影响风口出风面积。
3)通风空调系统严密性检测及保温节能措施
通风空调系统风管及部件安装完成后,应进行严密性试验。根据规范要求,进行风管漏光试验或漏风量测试。低压风管系统应进行漏光检测,中压风管系统应抽检漏风量。漏光检测时主要检查风管接缝四周边角、风管与风阀接口四周等。检测程序方式及检测结果应符合规范标准的规定。确认系统严密性符合要求后,对于需要进行保温节能的系统应该进行保温施工,保温材料的选择应符合设计规定。施工工艺应满足规范标准,保证施工质量及外观要求。
4)系统调试及试运行
通风空调系统调试应分两个阶段:单机试运转、联合试运转。
单机试运转即为通风空调单个系统的运行试验,包括风机等设备启动电源是否缺相、是否由于电源接反导致设备反转、控制回路显示是否正常、风量及风速是否符合要求等,尤其对于双速风机设备,需要确认高低速电源是否接反、电源相间是否接反等情况。
联合试运转主要是设备及其系统中的部件联动的问题,主要应与综合监控系统和消防控制系统进行配合,确保各个部件的正确连锁动作。需要掌握各系统的工作原理,确认各部件的正常工作状态,在紧急情况下需要什么系统发布命令使其做何动作,并联动相关设备启动或停止。
通风空调工程的事后质量控制
事后质量控制即为事后质量把关,以保证不良的工序或产品(甚至单位工程或整个工程项目)不进入下道工序、不进入市场。简单的说,事后质量控制就是在产品或工序质量出现问题时,对其做出的处理方式应当有利于整体工程的质量、安全要求,并使其全部流程化、制度化,避免不能放行的产品、工序让步放行,需要通过研究提出改进措施,使工程整体质量受控。如根据风管制作缺陷的类别、程度决定是让步接收抑或是报废处理重新制作,并反馈问题,提出改进措施。
结束语
通风空调工程是建筑工程质量和节约能源、保持生产生活环境良好的重要方面。根据笔者本人对于通风空调工程施工的经验,总结以上部分通风空调工程的质量控制要点和管理方法,希望能对行业质量起到一点积极的促进作用。由于笔者本人水平有限,以上内容有不足之处,望请各位专家提出指正。
范文二:空调与通风工程质量控制
空调与通风工程质量控制
通风中央空调系统采用的场合一般是大型酒店、证劵、银行、商场、综合办公楼等装饰比较高档的场所,对安装质量的要求较高,也是我们机电安装工程的施工难点。暖通工程的安装质量关系到后期建筑物的能否正常使用,对于专职技术人员来说责任重大。结合青岛“海情大酒店”通风与空调工程施工情况,遇到一些质量问题,谈谈在空调与通风系统工程安装中,质量控制方面主要注意环节。
1、 确定各专业之间的施工程序
设计有通风空调的工程一般安装专业较多,不可能由一家队伍施工,这就要通过甲
方和监理协调各施工专业施工优先程序,通风空调系统应排在重力流排水系统后,
即第二优先程序,其它有压排水、给水、消防、喷淋、强弱电等系统应让道于通风
空调管道,这样尽量减少空调水系统阻力和气阻现象,为工程后期顺利调试创造条
件。
2、 图纸审核
认真阅读通风空调图纸,并结合各专业包括装饰图纸,画出包括装饰造型在内的各
专业的平面综合布置图,进行比较、对照,提前发现图纸中存在的问题,及时和设
计人员沟通。
(1)、核查建筑图上各管道井、通风井、机房空间大小及位置,其空间是否能满足
设备或管道有序布置,有无检修位置。如果系设计安装吊顶式空调机房间,应核查
该处顶板与装修顶面之间的净高是否够设备安装;屋面或外墙上的排风口与新风口
间距是否足够,如排风口与新风口间距太近,容易造成空气短路,导致新风质量无
法保证;走廊等设备运输时需通过的地方是否能保证设备搬运至机房。
(2)、空调系统的选择。应建议业主和设计人员在酒店大堂、会议室、多功能厅等
对环境要求安静的地方,最好采用全空气系统。如果选择空气加水系统,容易造成
以下问题:一是这类房间天花一般造型较复杂,顶棚标高要求较高,安装空间紧张,
空调机排水管道放坡高度不够,冷凝水排放困难;二是机组噪声容易使现场环境较
噪。
(3)、新风井、排风井的选择。应建议业主和设计人员最好用风管代替。这样做有
两个好处:一是风管密封性好,表面光滑,可以减少空气阻力,保证新风质量,二
是土建施工与安装单位可能不是一家,可避免风管与井道交叉处封堵时互相推诿,
造成井道漏风现象发生。
(4)、末端设备的选型,如风机盘管、空调机型号、性能参数是否能保证该区域的
空气调节要求。风机盘管除客房因素外,其余宜选择高静压型,以取得较好的冷热
交换效果。
3、 材料质量控制
做好材料设备进场验收工作,对于风管、水管、保温材料、阀门、空调机均应对照
设计图纸和技术文件一一核查,并对空调机性能设备作抽样试验,检验其参数是否
与设计要求相符;阀门要进行强度和严密性试验。对于电动阀和设备电控箱需留有
与楼宇自控系统接口,消防用风机控制箱须有与消防监控中心联动接口,风机盘管
还应检查其水管连接方向是否与图纸一致。
4、 安装过程的质量控制
(1)支架制作安装。要注意所用吊杆、型钢规格是否符合规范要求,支架能否承受管道或设备的最大荷载,防腐处理是否合格,设备和大型管道吊架应穿楼板固定,竖向空调管道应设防滑支架,支架的坡度是否符合要求(严禁反坡)。
(2)风管安装平直,过变形缝或与设备连接处做软连接,应避免不必要拐弯造成阻力增大;水管安装平直,转弯或爬坡处尽量走45?弯头以减少空气驻留,过建筑变形缝接软管;有方向要求的阀门安装应注意是否与水流方向相一致,周围是否有开启空间,风机盘管阀门和过滤器应尽量把安装位置定在积水盘以内,以方便检修时排水。冷凝水排水管应单独成系统,不应与其它排水管共用。
(3)设备安装。设备安装前,机房地坪应已做好,墙面已粉刷完毕,设备基础验收合格。设备摆布方位应尽量与管道走向相对应,还应考虑设备四周是否有检修空间。风机盘管的安装应与装修顶棚高度以及送回风口位置相配合,其积水盘方位应与排水方向相一致。
(4)保温施工。保温工程也是暖通施工的重要环节,保温工艺质量不好直接导致系
统运行时产生的冷凝水滴漏,既造成能源浪费,又影响系统的正常使用。暖通保温
的难点在于水系统的施工,监理人员应严格要求施工方按程序施工,应在管道试压
合格、顶棚龙骨安装前完成保温施工,施工中容易产生质量问题的主要有阀门保温
层覆盖范围不够,保温材料与垫木粘接不严密,垫木不配套,垫木与管道的孔隙太
大。
(5)风口安装。暖通施工图应与装饰施工图进行会审,特别是会议室、多功能厅、
大堂等大空间天花造型复杂,风口、灯具、消防喷头的布置要与饰面造型相协调。
因此这类房间的风口在风管安装时先不开孔,等安装与装饰图纸会审风口定位后再
开。在实际施工中有些工程为了保证饰面造型的完美,要求风口按装修图定位或改
小截面,造成风管弯头太多,阻力增加,导致送风量不足,回风口噪声大等影响系
统使用功能等问题。因此技术人员一定要坚持在保证空调功能的前提下,才能同意
调整风口。还有就是风口和检修孔一般由装饰施工单位开孔,为避免遗漏或所开孔
尺寸或位置有误,应要求暖通安装单位在装饰图上标注风口尺寸及位置提供给装修
单位。
(6)预留孔洞封堵检查。暖通管道施工后留下许多穿墙或楼板预留洞,这些孔洞
一般不是安装单位自己封堵,如果封堵不好,会造成漏风,导致新风量不够,或废
气无法排空,换气无法进行。因此管理人员应及时督促相关单位作好封堵,避免遗
漏。
(7)做好成品保护。暖通专业大部分管线、设备都被吊顶隐蔽,由于本专业后序工序中还有别的专业在施工,如吊顶施工一般由装修单位承担,其施工过程中可能会对已完成的暖通专业管线造成一定破损。因此管理人员还应在装修施工完成后对顶棚里的隐蔽工程再进行复查,发现损坏之处及时要求安装单位修复。
5、 泵房安装
泵房是整个空调系统的心脏,泵房安装最能体现一支专业安装队伍的素质。怎样把泵房安装布置得合理、整齐、美观,要从下面几点着手。
(1)、设备基础定位。首先根据泵房的大小和管道的走向,把冷热水泵、冷却水泵、
水处理设备、稳压设备、冷水机组、集分水罐、换热器等的基础,画出大样图,合
理安排。
(2)、支架的安排。支架的形状和大小要统一、合理,方向要一致,支架是做好
管道安装的基础。
(3)、管道安装。阀门高度要一致,管道要成排、成线,保温结束后每一种管道
要贴上标签,标明本管道的性质、水流方向,标签的字体、大小要适中,黏贴标签
要整齐、贴在醒目的地方。
6、 系统调试
(1)风量不够。原因有调节阀未打开,风管未按图示走向安装,风机反转或过滤网
堵塞,或设备选型偏小。
(2)出风温度不达标。水系统阀门未打开,过滤器堵塞,供回水管空气未排净,主
机供水温度不符合要求。
(3)房间温度调节不符合要求,一是风量或出风温度不够,二是设备能力偏小。
(4)噪声过大。设备本身噪声超标,吊顶式空调机支架减震措施不当,风机出口未
装消声器,回风口截面太小。
(5)漏水。管道保温不符合要求,冷凝水排水管放坡不够,风机积水盘过于倾斜,
阀门密封不严, 排气阀漏水。
当然,施工中还会遇到这样或那样的情况,只要认真对待,勤于检查,重点控制上面的六条环节,一个通风空调工程应该能顺利完工。
济南: 朱建成
2009-11-31
范文三:通风空调工程质量控制
通风空调工程质量控制
通 风 空 调 工 程 质 量 控 制
1 2
张 朋 赵 幸 彩
1 河 北 省 安 装 工 程 公 司 ; 2 河 北 省 第 四 建 筑 工 程 公 司 河 北 石 家 庄 0 5 0 0 0 0
摘 要 : 随 着 现 代 信 息 化 发 展 和 不 断 的 科 技 创 新 , 人 们 对 于 生 产 生 活 的 环 境 要 求 越 来 越 高 , 对
环 境 工 程 的 要 求 也 越 来 越 严 格 和 重 视 , 所 以 对 于 通 风 空 调 工 程 施 工 的 技 术 和 质 量 提 出 了 更 为
苛 刻 的 要 求 。 同 时 , 质 量 问 题 也 往 往 与 安 全 事 故 有 直 接 联 系 , 所 以 , 工 程 中 质 量 管 理 显 得 极
为 重 要 。 随 着 社 会 的 发 展 及 法 律 法 规 的 不 断 健 全 , 工 程 质 量 控 制 的 手 段 及 监 督 措 施 也 在 不 断
完 善 , 但 是 由 于 经 济 成 本 、 人 员 素 质 、 设 计 的 多 样 化 等 原 因 , 通 风 空 调 工 程 质 量 控 制 还 有 些
不 尽 人 意 的 方 面 。 笔 者 通 过 自 身 在 实 际 工 程 中 的 实 践 经 验 对 通 风 空 调 工 程 的 质 量 控 制 进 行 了
系 统 总 结 , 希 望 对 于 从 事 通 风 空 调 质 量 管 控 的 人 员 及 施 工 企 业 提 供 些 许 借 鉴 作 用 。
关 键 词 : 通 风 空 调 ; 工 程 质 量 ; 控 制
A b s t r a c t : w i t h t h e d e v e l o p m e n t o f m o d e r n i n f o r m a t i o n a n d c o n t i n u o u s i n n o v a t i o n o f s c i e n c e a n d
t e c h n o l o g y , p e o p l e f o r p r o d u c t i o n a n d l i v i n g e n v i r o n m e n t d e m a n d i s h i g h e r a n d h i g h e r , t o t h e
r e q u i r e m e n t s o f e n v i r o n m e n t a l e n g i n e e r i n g i s b e c o m i n g m o r e a n d m o r e s t r i c t a n d a t t e n t i o n , s o f o r
t h e v e n t i l a t i o n a n d a i r c o n d i t i o n i n g e n g i n e e r i n g c o n s t r u c t i o n t e c h n o l o g y a n d q u a l i t y p u t f o r w a r d
m o r e s t r i n g e n t r e q u i r e m e n t sA t t h e s a m e t i m e , t h e q u a l i t y p r o b l e m s o f t e n a l s o a n d s a f e t y
a c c i d e n t s h a v e d i r e c t c o n n e c t i o n , s o , e n g i n e e r i n g q u a l i t y m a n a g e m e n t i s v e r y i m p o r t a n tW i t h t h e
d e v e l o p m e n t o f s o c i e t y a n d t h e l a w s a n d r e g u l a t i o n s , p e r f e c t , e n g i n e e r i n g q u a l i t y c o n t r o l m e t h o d s
a n d m e a s u r e s o f s u p e r v i s i o n i s b e i n g p e r f e c t e d , b u t b e c a u s e o f t h e e c o n o m i c c o s t , p e r s o n n e l
q u a l i t y , d e s i g n a n d o t h e r r e a s o n s , t h e d i v e r s i f i c a t i o n o f v e n t i l a t i o n a n d a i r c o n d i t i o n i n g
e n g i n e e r i n g q u a l i t y c o n t r o l s t i l l h a v e s o m e u n s a t i s f a c t o r y a s p e c t sT h e a u t h o r t h r o u g h t h e p r a c t i c e
o f t h e i r o w n i n t h e p r a c t i c a l e n g i n e e r i n g e x p e r i e n c e o f v e n t i l a t i o n a n d a i r c o n d i t i o n i n g e n g i n e e r i n g
q u a l i t y c o n t r o l s y s t e m a t i c a l l y s u m m a r i z e s , h o p e f o r v e n t i l a t i o n a n d a i r c o n d i t i o n i n g i n t h e q u a l i t y
c o n t r o l p e r s o n n e l a n d c o n s t r u c t i o n e n t e r p r i s e t o p r o v i d e s o m e r e f e r e n c eK e y w o r d s : v e n t i l a t i o n a n d a i r c o n d i t i o n i n g ; E n g i n e e r i n g q u a l i t yC o n t r o l
中 图 分 类 号 : T K 2 8 48 文 献 标 识 码 : A 文 章 编 号 : 2 0 9
5 - 2 1 0 4 ( 2 0 1 3 )
引 言
通 风 空 调 工 程 是 现 代 建 筑 工 程 的 必 要 组 成 部 分 。 随 着 现 代 信 息 化 发 展 和 不 断 的 科 技 创
新 , 人 们 对 于 生 产 生 活 的 环 境 要 求 越 来 越 高 , 对 环 境 工 程 的 要 求 也 越 来 越 严 格 和 重 视 , 所 以
对 于 通 风 空 调 工 程 施 工 的 技 术 和 质 量 提 出 了 更 为 苛 刻 的 要 求 。 同 时 , 质 量 问 题 也 往 往 与 安 全
事 故 有 直 接 联 系 , 所 以 , 工 程 中 质 量 管 理 显 得 极 为 重 要 。 随 着 社 会 的 发 展 及 法 律 法 规 的 不 断
健 全 , 工 程 质 量 控 制 的 手 段 及 监 督 措 施 也 在 不 断 完 善 , 但 是 由 于 经 济 成 本 、 人 员 素 质 、 设 计
的 多 样 化 等 原 因 , 通 风 空 调 工 程 质 量 控 制 还 有 些 不 尽 人 意 的 方 面 。 笔 者 通 过 自 身 在 实 际 工 程
中 的 实 践 经 验 对 通 风 空 调 工 程 的 质 量 控 制 进 行 了 系 统 总 结 , 希 望 对 于 从 事 通 风 空 调 质 量 管 控
的 人 员 及 施 工 企 业 提 供 些 许 借 鉴 作 用 。
1 、 通 风 空 调 工 程 质 量 的 事 前 控 制
通 风 空 调 工 程 施 工 质 量 的 事 前 控 制 与 所 有 工 程 的 事 前 准 备 工 作 相 同 , 主 要 包 含 以 下 几 个
方 面 : a图 纸 会 审 及 与 设 计 院 的 沟 通 ; b技 术 交 底 及 安 全 交 底 ; c进 场 材 料 的 质 量 把 关 ; e机 械 设 备 的 选 择 及 保 养 。
11 图 纸 会 审 及 与 设 计 院 的 沟 通
施 工 企 业 在 进 行 通 风 空 调 工 程 施 工 准 备 工 作 中 , 首 先 是 安 排 技 术 人 员 对 所 实 施 工 程 的 图
纸 进 行 会 审 , 从 技 术 层 面 了 解 所 承 接 工 程 的 工 程 范 围 、 施 工 内 容 、 技 术 要 求 、 材 料 要 求 等 。在 技 术 人 员 了 解 工 程 概 况 的 情 况 下 , 才 能 提 出 工 程 所 需 的 材 料 计 划 、 机 械 设 备 需 求 、 施 工 工
法 的 选 择 、 特 种 人 员 需 求 及 劳 务 的 总 需 求 量 等 , 以 达 到 设 计 要 求 的 质 量 标 准 及 相 关 要 求 。 另
外 , 图 纸 会 审 还 应 该 了 解 设 计 对 于 该 工 程 的 设 计 原 理 , 对 于 每 个 系 统 所 选 用 的 各 相 关 设 备 的
要 求 、 控 制 方 式 、 动 作 原 理 等 , 同 设 计 确 认 清 楚 , 以 便 设 备 选 型 能 够 做 到 完 全 符 合 标 准 , 避
免 由 于 设 备 选 型 有 误 带 来 后 续 调 试 时 出 现 问 题 。 后 期 调 试 过 程 中 的 不 符 合 要 求 对 于 施 工 企 业
的 更 改 难 度 非 常 大 , 所 以 施 工 企 业 要 尽 量 避 免 , 把 施 工 图 的 图 纸 会 审 做 扎 实 。 如 对 图 纸 中 每
个 通 风 空 调 系 统 的 风 机 设 备 、 空 调 设 备 的 参 数 详 细 了 解 , 统 计 风 阀 、 风 口 设 备 的 技 术 要 求 、
控 制 方 式 、 是 否 要 求 有 调 节 风 量 功 能 、 安 装 方 式 等 等 , 以 利 于 选 型 。 同 时 , 图 纸 会 审 要 确 认
防 火 分 区 、 防 烟 分 区 的 划 分 原 则 及 与 防 火 分 区 和 防 烟 分 区 相 关 的 技 术 和 质 量 要 求 。 预 留 孔 洞 、
预 埋 件 作 为 通 风 空 调 工 程 中 必 有 的 部 分 , 图 纸 会 审 时 应 现 场 踏 勘 比 对 , 有 问 题 及 时 提 交 监 理
及 设 计 单 位 进 行 解 决 。
12 技 术 交 底 及 安 全 交 底
在 工 程 进 行 施 工 前 , 技 术 负 责 人 要 对 所 有 参 与 施 工 的 人 员 进 行 技 术 交 底 及 安 全 交 底 , 并
要 求 带 班 工 长 要 有 一 定 的 技 术 水 平 , 了 解 通 风 空 调 工 程 施 工 的 基 本 原 理 和 原 则 , 严 谨 施 工 人
员 盲 目 作 业 。 技 术 交 底 内 容 要 求 表 明 质 量 标 准 要 求 、 施 工 参 考 图 集 做 法 及 质 量 控 制 要 点 , 如
对 于 风 管 的 加 工 制 作 要 求 、 法 兰 的 匹 配 互 换 性 要 求 、 风 阀 与 风 管 的 连 接 要 求 等 。 安 全 交 底 中
除 明 确 施 工 作 业 中 应 注 意 的 安 全 问 题 及 采 取 的 安 全 防 护 措 施 外 , 还 应 该 将 质 量 与 安 全 的 联 系
加 以 说 明 。 对 于 工 程 的 功 能 性 和 使 用 安 全 性 , 往 往 由 于 质 量 的 问 题 而 导 致 安 全 事 故 的 发 生 ,
例 如 消 防 质 量 安 全 事 故 、 高 空 作 业 质 量 安 全 事 故 等 等 。
13 进 场 材 料 的 质 量 把 关
进 场 材 料 的 质 量 同 整 个 工 程 的 质 量 息 息 相 关 。 对 于 工 程 所 使 用 的 原 材 料 、 成 品 半 成 品 、
构 配 件 等 要 进 行 严 格 的 检 查 验 收 , 建 立 管 理 台 账 ,
进 行 收 、 检 、 发 、 储 、 运 等 各 环 节 的 管 理
制 度 , 避 免 混 乱 和 不 合 格 的 原 材 料 使 用 的 工 程 上 。 例 如 针 对 风 阀 防 火 阀 的 不 同 种 类 、 不 同 型
号 、 不 同 系 统 进 行 存 放 , 避 免 由 于 管 理 混 乱 而 造 成 混 用 , 影 响 工 程 质 量 。 当 然 如 果 分 类 太 细 ,
会 影 响 仓 库 使 用 效 率 , 增 加 库 管 员 的 工 作 量 , 所 以 应 根 据 场 地 实 际 情 况 酌 情 分 类 存 储 。 但 是
对 于 每 单 位 原 材 料 、 设 备 必 须 进 行 有 效 的 标 识 , 严 格 按 照 标 识 进 行 收 发 领 用 。
14 机 械 设 备 的 选 择 与 保 养
机 械 设 备 包 括 施 工 机 械 设 备 、 工 具 等 。 要 根 据 不 同 的 工 艺 特 点 和 技 术 要 求 , 选 用 合 适 的
机 械 设 备 和 工 具 ; 正 确 使 用 、 管 理 和 保 养 好 机 械 设 备 、 工 具 。 为 此 要 健 全 “ 人 机 固 定 ” 制 度 、
“ 操 作 证 ” 制 度 、 岗 位 责 任 制 度 、 交 接 班 制 度 、 机 械 设 备 检 查 制 度 等 , 确 保 机 械 设 备 处 于 最
佳 使 用 状 态 , 保 证 设 备 精 度 、 使 用 安 全 , 保 证 施 工 质 量 满 足 精 度 要 求 。 如 风 管 制 作 加 工 设 备
的 精 度 控 制 、 维 修 与 保 养 ; 红 外 线 定 位 仪 的 精 度 控 制 等 。
2 、 通 风 空 调 工 程 的 事 中 质 量 控 制
事 中 质 量 控 制 是 指 在 施 工 过 程 中 进 行 的 质 量 控 制 。
事 中 质 量 控 制 的 策 略 是 全 面 控 制 施 工
过 程 , 重 点 控 制 工 序 质 量 。
21 施 工 企 业 应 认 真 做 好 工 序 的 自 检 、 互 检 、 交 接 检 检 查 。 企 业 自 检 是 发 现 质 量 问 题 的
主 要 来 源 , 但 是 要 杜 绝 只 查 不 改 , 或 改 不 到 位 。 如 风 管 加 工 制 作 过 程 中 , 加 工 人 员 要 自 检 风
管 成 形 标 准 、 法 兰 平 面 度 、 风 管 密 封 性 、 风 管 咬 口 牢 固 性 、 螺 钉 间 距 等 等 。 风 管 加 工 好 进 行
安 装 前 应 有 技 术 人 员 进 行 交 接 检 查 , 确 认 前 一 工 序 质 量 合 格 再 进 行 下 一 工 序 。
22 工 程 施 工 过 程 中 要 设 置 质 量 控 制 要 点 。 质 量 控 制 点 是 为 了 保 证 作 业 过 程 质 量 而 确 定
的 重 点 控 制 对 象 、 关 键 部 位 或 薄 弱 环 节 。 质 量 控 制 点 的 设 置 是 保 证 施 工 过 程 质 量 的 有 力 措 施 。
通 风 空 调 工 程 的 质 量 控 制 要 点 如 下 。
1 ) 风 管 制 作
a风 管 外 形 质 量 , 应 表 面 平 整 、 咬 口 牢 固 、 无 严 重 划 痕 、 法 兰 平 面 度 符 合 要 求 、 螺 钉 螺孔 间 距 满 足 标 准 、 尺 寸 偏 差 在 安 装 精 度 范 围 内 。 风 管 密 封 应 严 密 , 以 板 材 连 接 密 封 为 主 , 辅
以 密 封 胶 嵌 缝 , 密 封 胶 应 符 合 环 境 要 求 , 宜 涂 覆 在 风 管 的 正 压 侧 。
b矩 形 风 管 弯 管 的 制 作 , 一 般 应 采 用 曲 率 半 径 为 一 个 平 面 边 长 的 内 外 同 心 弧 形 弯 管 。 当
采 用 其 他 形 式 的 弯 管 , 平 面 边 长 大 于 5 0 0 m m 时 , 必 须 设 置 导 流 片 。
c风 管 加 固 符 合 标 准 规 范 要 求 。
d大 边 长 碳 钢 焊 接 风 管 宜 采 用 氩 弧 焊 , 并 矫 正 焊 接 变 形 , 加 固 可 靠 。
2 ) 风 管 及 部 件 安 装
a风 管 连 接 间 的 密 封 条 应 符 合 消 防 及 空 调 通 风 系 统 的 规 定 。 密 封 条 厚 度 根 据 风 管 的 连 接
方 式 确 定 。 对 于 承 插 连 接 的 复 合 风 管 由 于 连 接 间 距 较 小 , 可 以 采 用 密 封 胶 作 为 密 封 连 接 介 质 。
b风 管 与 风 阀 部 件 的 连 接 应 采 用 螺 栓 连 接 , 螺 栓 规 格 应 根 据 风 管 边 长 不 同 按 照 相 关 图 集
进 行 选 择 , 尤 其 是 防 火 阀 , 禁 止 使 用 自 攻 螺 丝 连 接 。 在 定 做 防 火 阀 时 , 应 将 风 管 与 风 阀 法 兰
的 螺 孔 制 作 规 则 统 一 一 致 , 保 证 互 换 性 , 避 免 由 于 不 匹 配 而 造 成 的 质 量 问 题 和 影 响 工 作 效 率 。
c风 阀 安 装 应 设 置 独 立 支 吊 架 , 尤 其 是 边 长 大 于 6 3 0 m m 的 防 火 阀 , 避 免 因 火 灾 时 风 管
变 形 而 影 响 性 能 。 支 吊 架 形 式 参 照 图 集 制 作 。 防 火 阀 的 安 装 方 向 、 位 置 应 正 确 。 防 火 分 区 隔
墙 两 侧 的 防 火 阀 , 距 墙 表 面 不 应 大 于 2 0 0 m m 。 防 火 阀 的 易 熔 片 应 朝 向 火 灾 危 险 性 较 大 的 一
侧 。
d远 控 多 页 排 烟 口 送 风 口 的 安 装 注 意 事 项 。 由 于 排 烟 口 ( 送 风 口 ) 由 带 有 一 定 厚 度 的
阀 体 和 铝 合 金 风 口 组 成 , 所 以 排 烟 口 ( 送 风 口 ) 安 装 于 风 管 上 时 , 应 从 风 管 开 口 处 安 装 法 兰
与 排 烟 口 ( 送 风 口 ) 连 接 , 禁 止 直 接 将 排 烟 口 ( 送 风 口 ) 安 装 与 风 管 内 部 , 影 响 风 管 通 风 面
积 , 或 将 风 管 开 口 处 制 作 与 排 烟 口 ( 送 风 口 ) 厚 度 相 同 的 风 管 短 管 , 将 排 烟 口 ( 送 风 口 ) 安
装 于 短 管 内 , 并 使 用 螺 栓 或 自 攻 螺 丝 连 接 牢 固 , 密 封 严 密 。 为 防 止 排 烟 口 ( 送 风 口 ) 的 重 量
过 重 导 致 风 管 变 形 或 受 损 , 排 烟 口 ( 送 风 口 ) 宜 单 独 设 置 吊 架 。 其 远 控 装 置 安 装 应 引 下 至 适
当 位 置 , 控 制 缆 绳 使 用 金 属 套 管 , 弯 曲 半 径 不 小 于 2 5 0 m m , 弯 曲 不 应 多 于 两 处 , 并 应 配 合
装 修 要 求 做 到 美 观 实 用 。
e风 管 穿 越 墙 体 时 , 预 留 孔 洞 的 尺 寸 应 比 风 管 截 面 的 每 边 尺 寸 大 1 0 0 m m , 并 用 不 燃 且 对
人 体 无 危 害 的 柔 性 材 料 封 堵 。 由 于 风 管 安 装 单 位 与 墙 体 砌 筑 单 位 往 往 不 是 同 一 施 工 企 业 , 平
行 施 工 时 要 求 单 位 之 间 配 合 密 切 , 并 应 做 好 成 品 保 护 工 作 。
f风 口 安 装 时 应 符 合 规 定 要 求 。 对 于 镂 空 吊 顶 内 安 装 的 风 口 , 需 要 注 意 风 口 的 安 装 位 置
不 得 与 装 修 吊 顶 的 部 件 重 叠 , 影 响 风 口 出 风 面 积 。
3 ) 通 风 空 调 系 统 严 密 性 检 测 及 保 温 节 能 措 施
通 风 空 调 系 统 风 管 及 部 件 安 装 完 成 后 , 应 进 行 严 密 性 试 验 。 根 据 规 范 要 求 , 进 行 风 管 漏
光 试 验 或 漏 风 量 测 试 。 低 压 风 管 系 统 应 进 行 漏 光 检 测 , 中 压 风 管 系 统 应 抽 检 漏 风 量 。 漏 光 检
测 时 主 要 检 查 风 管 接 缝 四 周 边 角 、 风 管 与 风 阀 接 口 四 周 等 。 检 测 程 序 方 式 及 检 测 结 果 应 符 合
规 范 标 准 的 规 定 。 确 认 系 统 严 密 性 符 合 要 求 后 , 对 于 需 要 进 行 保 温 节 能 的 系 统 应 该 进 行 保 温
施 工 , 保 温 材 料 的 选 择 应 符 合 设 计 规 定 。 施 工 工 艺 应 满 足 规 范 标 准 , 保 证 施 工 质 量 及 外 观 要
求 。
4 ) 系 统 调 试 及 试 运 行
通 风 空 调 系 统 调 试 应 分 两 个 阶 段 : 单 机 试 运 转 、 联 合 试 运 转 。
单 机 试 运 转 即 为 通 风 空 调 单 个 系 统 的 运 行 试 验 , 包 括 风 机 等 设 备 启 动 电 源 是 否 缺 相 、 是
否 由 于 电 源 接 反 导 致 设 备 反 转 、 控 制 回 路 显 示 是 否 正 常 、 风 量 及 风 速 是 否 符 合 要 求 等 , 尤 其
对 于 双 速 风 机 设 备 , 需 要 确 认 高 低 速 电 源 是 否 接 反 、 电 源 相 间 是 否 接 反 等 情 况 。
联 合 试 运 转 主 要 是 设 备 及 其 系 统 中 的 部 件 联 动 的 问 题 , 主 要 应 与 综 合 监 控 系 统 和 消 防 控
制 系 统 进 行 配 合 , 确 保 各 个 部 件 的 正 确 连 锁 动 作 。 需 要 掌 握 各 系 统 的 工 作 原 理 , 确 认 各 部 件
的 正 常 工 作 状 态 , 在 紧 急 情 况 下 需 要 什 么 系 统 发 布 命 令 使 其 做 何 动 作 , 并 联 动 相 关 设 备 启 动或 停 止 。
3 、 通 风 空 调 工 程 的 事 后 质 量 控 制
事 后 质 量 控 制 即 为 事 后 质 量 把 关 , 以 保 证 不 良 的 工 序 或 产 品 ( 甚 至 单 位 工 程 或 整 个 工 程
项 目 ) 不 进 入 下 道 工 序 、 不 进 入 市 场 。 简 单 的 说 , 事 后 质 量 控 制 就 是 在 产 品 或 工 序 质 量 出 现
问 题 时 , 对 其 做 出 的 处 理 方 式 应 当 有 利 于 整 体 工 程 的 质 量 、 安 全 要 求 , 并 使 其 全 部 流 程 化 、
制 度 化 , 避 免 不 能 放 行 的 产 品 、 工 序 让 步 放 行 , 需 要 通 过 研 究 提 出 改 进 措 施 , 使 工 程 整 体 质
量 受 控 。 如 根 据 风 管 制 作 缺 陷 的 类 别 、 程 度 决 定 是 让 步 接 收 抑 或 是 报 废 处 理 重 新 制 作 , 并 反
馈 问 题 , 提 出 改 进 措 施 。
结 束 语
通 风 空 调 工 程 是 建 筑 工 程 质 量 和 节 约 能 源 、 保 持 生 产 生 活 环 境 良 好 的 重 要 方 面 。 根 据 笔
者 本 人 对 于 通 风 空 调 工 程 施 工 的 经 验 , 总 结 以 上 部 分 通 风 空 调 工 程 的 质 量 控 制 要 点 和 管 理 方
法 , 希 望 能 对 行 业 质 量 起 到 一 点 积 极 的 促 进 作 用 。 由 于 笔 者 本 人 水 平 有 限 , 以 上 内 容 有 不 足
之 处 , 望 请 各 位 专 家 提 出 指 正 。
范文四:通风空调工程质量控制流程图
通风空调工程质量监理的工作流程
按要求填写各栏目: 熟悉图纸,将工艺图与土 , 施工组织设计,施工方案 建图对照,核查有无矛盾填写开工申请 , 工人、技术人员数量 或参加图纸会审 , 机械品种,数量 监理工程师 承包方 , 承包方,分包方资质证件
审核内容包括:
, 承包方分包方的资质证件 审核开工申请 , 有关工种操作人员的上岗监理工程师 证书
, 施工组织设计施工方案等 不同意 承包方修改完善 审核结果
同意
制作零部件,预埋件及隐蔽工程
监理工程师
按设计要求验收施工材料或器材,
必要时作材性试验
监理工程师或监理试验工程师
不合格 整改 审批结果
合格
现场验收制作的零部件,预埋件及
隐蔽工程
监理工程师
不合格 整改 验收结果
合格
签字零部件制作质量验收单或隐蔽
工程验收单
监理工程师
部件及设备准备安装 安装现场验收内容为: 设备开箱检查内
设备基础,管道孔阀,容:
预埋件坐标位置,标高,设备型号规格是设备开箱验收 安装现场验收(土与大小等 否与设计相符,业主、承包方、监安装中间交接验收) 设备外观是否完理工程师 承包方、监理工程师 好无损,零配件
是否齐全等
不合格 整改 验收结果 验收结果
合格 合格
部件及设备安装
承包方
部件及设备安装质量验收
监理工程师
不合格 整改 验收结果
合格 签认安装质量验收单
监理工程师
系统强度、严密性、真空度等试验及敏感件
试验,电气耐压试验等
承包方
现场检查或复制
监理工程师
不合格 整改 检查结果
合格 签认试(耐)压报告单
监理工程师
系统单机无负荷试车
承包方
现场检查或复测 各有关专业监理工程师
不合格 整改 审核测试结果
合格
签认单机试运转记录
监理工程师
由业主负责,对系统进行 负荷试验测定与调整
业主、设计单位、承包方、监理工程师
不合格 整改 测试结果
合格
签认测定数量与调整报告 业主、承包方、监理工程师
审核该单项所有质量检验评定表及评定等级
监理工程师
审核竣工资料
监理工程师
竣工交付使用
范文五:质量控制流程-通风空调工程质量控制流程
按要求填写各栏目: 熟悉图纸,将工艺图与土 , 施工组织设计,施工方案 建图对照,核查有无矛盾填写开工申请 , 工人、技术人员数量 或参加图纸会审 , 机械品种,数量 监理工程师 承包方 , 承包方,分包方资质证件
审核内容包括:
, 承包方分包方的资质证件 审核开工申请 , 有关工种操作人员的上岗监理工程师
证书
, 施工组织设计施工方案等 不同意 承包方修改完善 审核结果
同意
制作零部件,预埋件及隐蔽工程
监理工程师
按设计要求验收施工材料或器材,
必要时作材性试验
监理工程师或监理试验工程师
不合格 整改 审批结果
合格
现场验收制作的零部件,预埋件及
隐蔽工程
监理工程师
不合格 整改 验收结果
合格
签字零部件制作质量验收单或隐蔽
工程验收单
监理工程师
部件及设备准备安装 安装现场验收内容为: 设备开箱检查内
设备基础,管道孔阀,容:
预埋件坐标位置,标高,设备型号规格是设备开箱验收 安装现场验收(土与大小等 否与设计相符,业主、承包方、监安装中间交接验收)
设备外观是否完理工程师 承包方、监理工程师
好无损,零配件
是否齐全等
不合格 整改 验收结果 验收结果
合格 合格
部件及设备安装
承包方
部件及设备安装质量验收
监理工程师
不合格 整改 验收结果
合格
签认安装质量验收单
监理工程师
系统强度、严密性、真空度等试验及敏感件
试验,电气耐压试验等
承包方
现场检查或复制
监理工程师
不合格 整改 检查结果
合格
签认试(耐)压报告单
监理工程师
系统单机无负荷试车
承包方
现场检查或复测
各有关专业监理工程师
不合格 整改 审核测试结果
合格
签认单机试运转记录
监理工程师
由业主负责,对系统进行
负荷试验测定与调整 业主、设计单位、承包方、监理工程师
不合格 整改 测试结果
合格
签认测定数量与调整报告 业主、承包方、监理工程师
审核该单项所有质量检验评定表及评定等级
监理工程师
审核竣工资料
监理工程师
竣工交付使用